DESCRIPTION

Welding Construction Notes for Spiral Steel Pipe

This specification applies to on-site butt welding,installation and construction of large-diameter spiral steel pipes for water supply,drainage,gas transmission,pile foundation and utility projects.

1.Pre-Welding Preparation

Clean the groove and nearby area thoroughly to remove rust,oil,moisture,dust and coating defects.

Process pipe ends with standard V-grooves;ensure flatness and no burrs or notches.

Align pipe axes strictly,control misalignment within allowable tolerance,and fix with tack welds evenly distributed.

Preheat alloy and high-grade steel pipes to 80–120°C to prevent cold cracking.

Set up wind shields when wind speed exceeds 0.5m/s to avoid porosity.

Check welding machines,cables and ground connections for reliable insulation.

2.Welding Operation Requirements

Adopt qualified welding procedures and matching electrodes/wires.

Complete root pass fully before removing internal aligners;finish at least 50%of root pass for external aligners.

Maintain stable arc length and proper heat input to avoid undercut,overlap,burn-through or incomplete fusion.

Control inter-pass temperature;remove slag and clean each bead before the next layer.

Avoid sudden quenching;do not strike arcs on base metal surfaces.

For long seams,use symmetrical and segmented welding to reduce deformation.

3.Post-Welding Treatment&Inspection

Allow natural cooling;do not splash water or apply external force during cooling.

Perform visual inspection first:welds shall be well-formed,smooth,free of cracks,porosity,slag inclusions and pits.

Conduct NDT(RT/UT/MT/PT)as required by project standards.

Repair defective areas per approved procedures;re-inspect after repair.

Carry out pressure testing per design code after welding completion.

4.Safety&Site Management

Operators must hold valid welding certificates and use PPE.

Prohibit welding on pipes under pressure or with flammable residues.

Ensure good ventilation in confined spaces;monitor for harmful fumes.

Prepare fire-fighting equipment;keep combustibles away from the work zone.

Handle lifting and supporting safely to prevent vibration or shifting during welding.


HOT PRODUCTS
MORE
Stainless Steel Elbow
Stainless Steel Elbow
Equal Tee
Equal Tee
Flange
Flange
Reducer
Reducer
ABOUT US
 
The company mainly produces a full range of pipe fittings such as elbows, flanges, tees, heads, reducers, and bent pipes. At the same time, it also produces pipe products such as spiral steel pipes, straight seam steel pipes, and coated steel pipes. The specifications are complete and the materials are diverse. It can be produced according to national standards, industry standards, and customer customization needs to meet the pressure, anti-corrosion, and connection requirements of different working conditions.
DETAILS
CONTACT US
 
TEL : 8615933281888
ADD : Mengcun Hui Autonomous County, Cangzhou City, Hebei Province, China
Rantie